Location

Is located in Huallanca district, Bolognesi province, Ancash region, the coordinates are:

East

North

270,000

8'913,000

272,000

8'917,000

Access

The access to Pucarrajo Unit is following the asphalt road Panamericana Norte, road to Huaraz city and road to Antamina mine. The route Lima – Paramonga – Conococha – Pucarrajo has a longitud of 425 Km. Is made in 9 hours and only the last 9 Km. Are road surfacing.

Property

Nowadays, the Pucarrajo Unit  is integrated for 11 miner concessions, which the company has in grant quality, named Lucero, Maria del Pilar, Maria del Pilar numero Tres, Maria del Rosario, Maria del Rosario numero Tres, Maria del Rosario numero cinco, Maria del Rosario numero 6, Nuevo Peru, Santa Juana cuatro, Santa Juana numero tres, and Excepcion Santa Juana numero 5; besides the two miner concessions, mine Tuco and Graal, which the company is entitle.

Additionally, the company has a registered entitle of the concession of benefit Don Froylan, that authorize the plant operation to 500 Ton/day of capacity.

Geology

The geological frame Pucarrajo is located in a sedimentary basin folded in anticline and syncline something symmetric, Andean orientation  NW-SE, with formation from inferior to superior cretaceous that outcrops in the region. From de ancients to the new ones this formations are: Chimu, Santa, Carhuaz, Ferrst, Pariahuanca, Chulec and Pariatambo, all intruded by Ishpag stock of granodiorite-diorite composition that in contact with sedimentary formation provoke  the hydrothermal metamorphism  which aureole is 2.0 x 1.7 forming chalcosilicated, development of rocks like marble, hornfels, and quartzite; the intrusive placed taking ply and regional faults inverse like  Huari Jirca, and San Marcos. The primary minerals from de ore are constituted by marmatite, galena (lead ore) and in less amounts chalcopyrite, joined for pyrrhotite, pyrites and magnetite.

Pucarrajo mine is a polimetalic layer of Zn, Pb,, Ag, skarn type, originated by metasomatic replacement located in limestone  sequences from Chulec formation of Albiano inferior, in which has formed  irregular bodies, stratum and veins at deposition temperature from mesothermal to epithermal. The continuity horizontal and vertical is sometimes truncated to show up meters ahead or in depth. Have dimensions that may vary from a few meters to 40 – 60 from the horizontal and from a few meters to 240 mt in the vertical.

Exploration and Development Program

The mineral resources and the ore reserves from Pucarrajo Unit, requires an appropriate exploration program, framed inside the geological characteristics  of the layer, which has been designed to explore the bodies and stratum mineralized through galleries, cross heading and diamantine perforation.

Reserves and Natural Resources

See our page of Reserves & Resources. Click Here (only in Spanish)

Mine

The Pucarrajo Unit  has nowadays as principal production zones, the areas denominated: Sabrina, Pucarrajo, Carmencita and Tania, the most important are  Sabrina and Tania.

The exploitation method  used is the provisional storage because so the mineral as the boxes are reported as competent. It has visited active stopings and observe that the boxes and minerals are competent.  This  method, has the disadvantage of using a lot of workmanship, the productivity is from middle to low and the great part of the mineral remains in the stopings during a long time, but has the advantage  that the investment in equipment is lower and the mineral load is made from the hoppers in a easy way. Besides the descript method allows a high recovery and low dilution. The selected method is the adequate because permits control the dilution in spite of the boxes are irregular and have fractured zones, where is necessary use sustain.

The perforation is made using perforators Jack Leg and Stoper. The blast is made with Anfo and dynamite and for the loading is used Scooptrams of 3.5 yd3. The transport to the surface is made with trucks of 15 mt3.

The main ventilation is forced and the energy used come from the red as well from the Hydroelectric Central Pacarenca

 Plant

See FlowSheet

The processing is realized in the treatment plant Don Froylan, the most relevant characteristics are:

Feed  hopper with 150 Ton capacity with  a plate feeder of 36” x 10”, a primary jaw crusher of 10” x 36” and a secondary cone crusher SH of 3” diameter with their respective shaking screen that works in closed circuit. To get a ¾ product that is stored in a 500 Ton capacity hopper.

The milling circuit consists of a bar mill of 5” x 12”, that operates on a open circuit and for the re-milling a 6” x 6” ball mill that operates in closed circuit with a 5” x 4” pump and cyclones of 12”, to circulate and  feed to flotation process.

The flotation will be composed by 2 circuit, the Pb circuit that is constituted  for 2 Rougher cells of 100 ft3. the foams pass by the cleaning cells of 18 ft3 in 3 stages, being the foams from the last stage the Pb concentrate. The tailings from the cleaning cells are sent to a bench of cells Scavager of 18 ft3 and the foams return to the Rougher stage. The tailings with the tailings from the Rougher flotation pass to a conditioned tanks of  Zinc.

The Zinc circuit comprehend a unitary cell follow of four cells Rougher of 100ft3. The foams from this cells pass through cleaning cells in four stages. The  foams from the fourth stage constitute the Zn concentrate. The tailings from the cleaning stage pass to a bench of cells Scavenger, formed by four cells of 18 ft3, the foams return to the Rougher cells. The tailings with the tailings from Rougher flotation conform the final tailings that is sent to the tailings field. 

The Zn and Pb concentrates are thickened and filtrated and dispatch in bulk in trucks  endowed with adequate security elements.

The tailings are disposed in a near tailings field, that use the method of central line with use of cyclone. The settling water are conducted to a storage well, from here the water is recirculated  totally to the concentrate plant. The present tailings deposit has an storage capacity enough to December 2007. Nowadays the company is in the process of contract the enginery services and environmental impact studies for a new tailings deposit that is going to have a capacity of 1.8 millions Tons, the new deposit allowed store tailings for 6 years more, the construction of this deposit is foreseed to begin in 2006, after have complete the requirements that the Energy and Mine Ministry asks for this kind of structures.

 

 Minera Huallanca - Copyrigth © 2007   HOME           |            EMAIL |       SITE MAP